Lanco Amarkantak Power located near Pathadi Village on Korba-Champa State Highway in Chhattisgarh, is a coal fired thermal based project, divided in two phases.
Phase I
Total Capacity |
: |
2 X 300 MW (600 MW) |
Fuel Source (Coal) |
: |
South Eastern Coal Fields |
Water Source | : |
River Hasdeo |
Plant Off-taker | : |
PTC India Limited |
Phase II
Capacity |
: |
2 X 660 MW (1320 MW) |
Fuel Source (Coal) |
: |
South Eastern Coal Fields |
Water Source |
: |
River Hasdeo |
Clearances |
: |
All Major statutory clearances in place |
EPC Contractor |
: |
Lanco Infratech Limited |
|
|
|
Status |
|
|
|
|
|
BTG
(Boiler, Turbine & Generator) |
: |
|
- Boiler Unit-3 - Structure erection completed, Pressure parts erection in progress, welding joints approx. 55% completed.
- Boiler Unit-4 - Structure erection completed, Pressure parts erection to be started.
- ESP Unit-3 - Collecting Electrode erection in progress
- ESP Unit-4 - Collecting Electrode erection completed.
- Boiler Aux Unit-3 - Coal Mill, Fans major parts erection completed.
- Boiler Aux Unit-4 - Coal Mill & Fans erection in progress.
- TG Erection Unit-3 - Condenser erection & Stator lifting completed. Turbine erection in progress.
- TG Erection Unit-4 -Condenser erection in progress.
- TG Aux Unit-3 - Deaerator, Heaters erection completed.
- TG Aux Unit-4 - HP Heater erection completed.
|
|
|
|
BOP
(Balance of Plant) |
: |
|
- Chimney shell construction completed & flue can erection work in progress.
- Coal handling plant, Fuel oil handling system, Water system, Ash handling system – Civil construction work in progress.
|
|
|
|
Electrical and C&I |
: |
|
- Unit Main Control Building erection completed. DCS erection completed for unit #3.
- LT & HT Switchgear erection completed & Transformer for unit #3 erection in progress.
- Erection in Switchyard & Switchyard Control Room completed.
- Transmission line erection work in progress.
|