is a coal fired thermal power project with two super critical units of 660 MW each, located near Mandva, Wardha District, Maharastra
Total Capacity | : |
2x660 MW (1320 MW) |
Fuel Source |
: |
From South Eastern Coal Fields |
Water Source | : |
From Lower Wardha reservoir |
Clearances |
: |
All major Clearances in place |
EPC Contractor |
: |
Lanco Infratech Limited |
Status |
|
BTG (Boiler, Turbine & Generator) |
Unit No1 |
: |
|
- Boiler Unit - 1: Boiler Structure erection completed. Ceiling Girder is ready for erection
- ESP Unit - 1: Structure erection work is in progress. Hopper erection is completed
- PHB Unit - 1: TG Deck Casting completed. EOT crane erection completed. Balance structure work in progress
|
Unit No 2 |
: |
|
- Boiler Unit - 2: Boiler Structure erection completed. Ceiling Girder is ready for erection
- ESP Unit - 2: Civil Foundation completed
- PHB Unit - 2: TG Deck casting in progress, EOT crane erection completed balance structure work in progress
|
Bunker, Tower Cranes |
|
|
|
Unit No. 1&2 |
: |
|
- Bunkers: Total 8 Nos. bunker to be completed out of which 6 bunkers fabrication is in progress
- Out of 6, pre-fabrication of 2 bunker assembly completed & erection of 1 bunker in progress
- Tower Cranes: 2 nos. of 80 Ton capacity of Tower crane for Boiler & 2 nos. of 12 ton capacity crane for ESP erected
|
BOP packages (FOHS,DM Plant, etc) |
Unit No. 1&2 |
: |
|
- DMPT: Vessel erection & building structural works in progress
- CW Pipe Line: Out of 400 spools, fabrication of 346 spools & erection of 264 spools competed
- ASH water Pipe Line: Supplies are in progress
- Chimney Flue Can and pre-fabrication assembly of structure: Out of 1200 tones, around 200 Tons of pre-fabricated assembly of Cans and structure is completed
- Hot Water Pipe Line for IDCT 1 & 2: Pre-fabrication of pipeline in progress is in progress
|
CIVIL |
|
|
|
Chimney / Flue can |
: |
Chimney concreting done up to 30 meters |
Switch yard and Control Room |
: |
70 % civil work already completed. 330 out of about 499 footing are completed for equipment placement |
Balance of plant civil works |
: |
DM Plant, ETP,WTP,FOHS,CT,CWPH: Civil works completed up to Column and Floor Beam level |
TG deck # 1&2 |
: |
TG#1 already completed and TG#2 80% completed |
Transformer yard |
: |
40% of civil works completed |
Coal handling system, incl. Wagon tippler |
: |
Crusher House foundation completed. Wagon Tippler raft completed. Around 10% civil works completed |
|
|
|
|
|