Lanco Vidarbha Thermal Power Ltd
Untitled Document
 
Profile Corporate Insolvency Resolution Process of LVTPL
Sl No
Name
1
2
3
4
5
6
7

Lanco Vidarbha Thermal Power is a coal fired thermal power project with two super critical units of 660 MW each, located near Mandva, Wardha District, Maharastra

Total Capacity : 2x660 MW (1320 MW)
Fuel Source : From South Eastern Coal Fields
Water Source : From Lower Wardha reservoir
Clearances : All major Clearances in place
EPC Contractor : Lanco Infratech Limited
Status  
BTG (Boiler, Turbine & Generator)
Unit No1 :  
  • Boiler Unit - 1: Boiler Structure erection completed. Ceiling Girder is ready for erection
  • ESP Unit - 1: Structure erection work is in progress. Hopper erection is completed
  • PHB Unit - 1: TG Deck Casting completed. EOT crane erection completed. Balance structure work in progress
Unit No 2 :  
  • Boiler Unit - 2: Boiler Structure erection completed. Ceiling Girder is ready for erection
  • ESP Unit - 2: Civil Foundation completed
  • PHB Unit - 2: TG Deck casting in progress, EOT crane erection completed balance structure work in progress
Bunker, Tower Cranes      
Unit No. 1&2 :  
  • Bunkers: Total 8 Nos. bunker to be completed out of which 6 bunkers fabrication is in progress
  • Out of 6, pre-fabrication of 2 bunker assembly completed & erection of 1 bunker in progress
  • Tower Cranes: 2 nos. of 80 Ton capacity of Tower crane for Boiler & 2 nos. of 12 ton capacity crane for ESP erected
BOP packages (FOHS,DM Plant, etc)
Unit No. 1&2 :  
  • DMPT: Vessel erection & building structural works in progress
  • CW Pipe Line: Out of 400 spools, fabrication of 346 spools & erection of 264 spools competed
  • ASH water Pipe Line: Supplies are in progress
  • Chimney Flue Can and pre-fabrication assembly of structure: Out of 1200 tones, around 200 Tons of pre-fabricated assembly of Cans and structure is completed
  • Hot Water Pipe Line for IDCT 1 & 2: Pre-fabrication of pipeline in progress is in progress
CIVIL      
Chimney / Flue can : Chimney concreting done up to 30 meters
Switch yard and Control Room : 70 % civil work already completed. 330 out of about 499 footing are completed for equipment placement
Balance of plant civil works : DM Plant, ETP,WTP,FOHS,CT,CWPH: Civil works completed up to Column and Floor Beam level
TG deck # 1&2 : TG#1 already completed and TG#2 80% completed
Transformer yard : 40% of civil works completed
Coal handling system, incl. Wagon tippler : Crusher House foundation completed. Wagon Tippler raft completed. Around 10% civil works completed
       
 
Half Yearly EC Report :
Environment Clearance Extension and amendment letter
Environment Clearance Order

Contact Address

 
Head Office :

Lanco Vidarbha Thermal Power Ltd
Unit No. 407, 4th floor,
Meadows, Sahar Plaza,
Andheri – Kurla Road, J. B. Nagar,
Andheri (E), Mumbai – 400 059
Phone + 91-22-61111300 
Fax +91 22-61111301
info.power@lancogroup.com

Plant Office :

11th Milestone,
Belgaon-Mandwa Road,
PO  Mandwa, Dist Wardha,
Maharashtra -422001
Phone +91-715-2283715
Fax +91-715-2240259

     


Contact Us || SiteMap
© Lanco Group, All Rights Reserved. |
Disclaimer
SHARE: 
twitter facebook linkedin youtube email post thoughts